PT. Satyamitra Surya PerkasaProject Control Manager
Jul. 2017 - Dec. 2018
Winteco Constructions Sdn. Bhd.Project Control Manager
Sep. 2016 - Dec. 2016Johor, Malaysia• Establishing and developing the Project Control System.
• Updating, monitoring & controlling for quantity produce and progress achievement.
• Updating, monitoring and controlling of Project schedule against the schedule project base line (planning schedule).
• Establishing the Project Budget
PT. Truba Jaya EngineeringProject Control Lead
Dec. 2016 - Jul. 2017South Kalimantan Province, Indonesia• Establishing Project Budget.
• Developing Project Master Schedule.
• Updating, monitoring & controlling for quantity produce and progress achievement.
• Updating, monitoring and controlling of Project schedule against the schedule project base line (planning schedule).
• Monitoring and Controlling the project expenditures or cost against the approved budget. • Preparing Project Reports
HATCH IndonesiaSenior Project Control Eng.
Dec. 2014 - Apr. 2016Jakarta• A strong personnel commitment to safety
• Project Master Schedule
o Maintaining, optimizing and monitoring progress identity and resolve issues
• Level 4 project Schedule
o Developing, maintaining and optimizing level 4 project schedules as required by the Project’s Project Control Plan, progress monitoring, highlight and resolve schedule issues.
o Analyze contractor level 4 schedule in weekly and incorporate updates in the project schedule.
• Project master schedule monitoring and updating
o Maintaining and optimizing schedule, monitoring progress, highlight and resolve schedule issues.
o Generate all progress curves.
o Developing and maintaining commodity and resource profile.
o Extract and publish detailed working schedule.
o Extract and publish 2-week look ahead schedule.
o Monitor slippages and critical and near critical paths and discuss with lead for resolution.