Saudi Binladin Group (SBG)Senior Architectural Engineer (Coordinator)
Oct. 2005 - Apr. 2011Jeddah, Makkah, Saudi ArabiaProjects: • King Abdullah 3rd Haram Expansion
• King Abdulaziz International Airport (Hajj Terminal, General Aviation)
• Improvement OfJamarat Area Bridge in Mena (Mekkah)
• Masa’a Extension Project
• King Abdullah University for Science And Technology ● Improved the cost control codes & effectively updated the cost logs to keep and maintain as per budgeted amounts.
● Execution quantity of steel handrails, flooring, cladding, false ceiling, glass partition, & doors.
● Ensured project completion within the budget and time limits, as per international quality standards set and to the satisfaction of Clients
● Executed complete packages of finishing works from initiation to close out and handover to client.
● Monitored and Controlled sub-contractor performance & ensured adherence to all requirements of applicable codes,specifications, & contract drawings.
● Undertaken daily site checks to ensure conformance to quality & safety norms and as per the budgeted costs.
● Prepared and raised to the Construction Manager the replies on related non-conformance reports NCR’s.
● Created work schedules, Cost estimation and resources histogram.
● Ensured that project complied with International and local regulations as well as revised project design as necessary.